Just so everyone is aware, a TOY cell is a macro site set up inside a Sprint MSC or DDC that is used to test, evaluate and train. It is not intended to be usable even outside the building. Sometimes they can be usable a few feet outside the building, but I've never heard of an instance of someone using a TOY more than a block away.

 

Often TOYs are locked down and the public cannot authenticate with the network on them. We mark TOY cells on our maps so people realize it is not a public macro site. We allow them on our maps more as informational to see where Sprint's DDC and MSC's are located. Not so much for locating signals.

 

Robert via Samsung Note 8.0 using Tapatalk Pro

  • Like 5
Link to comment
Share on other sites

Just so everyone is aware, a TOY cell is a macro site set up inside a Sprint MSC or DDC that is used to test, evaluate and train. It is not intended to be usable even outside the building. Sometimes they can be usable a few feet outside the building, but I've never heard of an instance of someone using a TOY more than a block away.Often TOYs are locked down and the public cannot authenticate with the network on them. We mark TOY cells on our maps so people realize it is not a public macro site. We allow them on our maps more as informational to see where Sprint's DDC and MSC's are located. Not so much for locating signals.Robert via Samsung Note 8.0 using Tapatalk Pro

So there's a training center in Waipahu?

 

Sent from my SM-N900P using Tapatalk

 

 

Link to comment
Share on other sites

So there's a training center in Waipahu?

 

Sent from my SM-N900P using Tapatalk

No. It is a Data Center. They have a TOY unit there. I explained what a TOY is used for.

 

Robert via Samsung Note 8.0 using Tapatalk Pro

 

 

  • Like 1
Link to comment
Share on other sites

No. It is a Data Center. They have a TOY unit there. I explained what a TOY is used for.

 

Robert via Samsung Note 8.0 using Tapatalk Pro

Street view of the "data center" on kahuhale st Posted Image

 

Sent from my SM-N900P using Tapatalk

 

 

Link to comment
Share on other sites

Street view of the "data center" on kahuhale st Posted Image

 

Sent from my SM-N900P using Tapatalk

I'm not in the mood to be mocked. I think you have completely misunderstood my posts. I am discussing how the one accepted LTE site on our maps is not actually a site and is not broadcasting to the public. You are discussing a Sensorly report. I am trying to explain to you that the signal from Sensorly IS NOT COMING FROM THE DATA CENTER.

 

If any other phantom signals appear, they also will not be coming from the data center. The Hawaii market is receiving NV deployments. The signal could very well be coming from a site in progress. I try to run around and provide helpful information to 98 markets. I don't appreciate being "mocked" by you for giving you good information about yours.

 

Robert via Samsung Note 8.0 using Tapatalk Pro

 

 

  • Like 3
Link to comment
Share on other sites

Hawaiian time for the permits.  None of the permits that is approved by the county is being worked on.  You can tell by no inspection date or start or completion time for the permits.  Only 3 permits approved by the county so far.  Permits are moving faster on the Maui, Kauai, and Big Island.  I is funny the permit approved for Maui county is for Molokai and not schedule to be complete for 30 years. (permit have the date 2043 year for completion) .  Now that is Hawaiian Time.

  • Like 2
Link to comment
Share on other sites

  I is funny the permit approved for Maui county is for Molokai and not schedule to be complete for 30 years. (permit have the date 2043 year for completion) .  Now that is Hawaiian Time.

 

:rofl:

Link to comment
Share on other sites

I'm not in the mood to be mocked. I think you have completely misunderstood my posts. I am discussing how the one accepted LTE site on our maps is not actually a site and is not broadcasting to the public. You are discussing a Sensorly report. I am trying to explain to you that the signal from Sensorly IS NOT COMING FROM THE DATA CENTER.

 

If any other phantom signals appear, they also will not be coming from the data center. The Hawaii market is receiving NV deployments. The signal could very well be coming from a site in progress. I try to run around and provide helpful information to 98 markets. I don't appreciate being "mocked" by you for giving you good information about yours.

 

Robert via Samsung Note 8.0 using Tapatalk Pro

Not mocking you, just trying to understand how that data point got that gps data there

 

Sent from my SM-N900P using Tapatalk

 

 

Link to comment
Share on other sites

I'm probably not the only one who got the msg that the "new network will be largely completed in your area...", right?  does this finally mean lte is right around the corner?

In Hawaii no way!

 

Everyone in the states have been getting that text. I got it too.Sprint unfortunately sends it to people all over the country.

 

I don't blame people being mad and leaving Sprint. Sprint gave their customers a date that their network will be completed in 30 days which for some markets it could be true. But for other markets it's almost impossible to finish the network in 30 days. When the 30 days are up, people will be even more angry because they've been lied too. Now that competition like T Mobile is offering to pay your early termination fee, these angry customers (which will be a lot) will switch carriers. Sprint SHOULD HAVE NEVER sent this text. It will confuse and mislead the customers. Bad business move.

 

For example Hawaii is farrrrrrr from being finished. Permits in this state really take forever to be approved.

Link to comment
Share on other sites

In Hawaii no way!

 

Everyone in the states have been getting that text. I got it too.Sprint unfortunately sends it to people all over the country.

 

I don't blame people being mad and leaving Sprint. Sprint gave their customers a date that their network will be completed in 30 days which for some markets it could be true. But for other markets it's almost impossible to finish the network in 30 days. When the 30 days are up, people will be even more angry because they've been lied too. Now that competition like T Mobile is offering to pay your early termination fee, these angry customers (which will be a lot) will switch carriers. Sprint SHOULD HAVE NEVER sent this text. It will confuse and mislead the customers. Bad business move.

 

For example Hawaii is farrrrrrr from being finished. Permits in this state really take forever to be approved.

I get what you're saying. And I pretty much agree. However, please be a little more careful how you post critical Sprint comments. Someone may mistake that for a rant, which would be against the S4GRU posting guidelines.

 

Robert via Nexus 5 using Tapatalk

 

 

Link to comment
Share on other sites

Hawaiian time for the permits.  None of the permits that is approved by the county is being worked on.  You can tell by no inspection date or start or completion time for the permits.  Only 3 permits approved by the county so far.  Permits are moving faster on the Maui, Kauai, and Big Island.  I is funny the permit approved for Maui county is for Molokai and not schedule to be complete for 30 years. (permit have the date 2043 year for completion) .  Now that is Hawaiian Time.

You know they approve they double digit pay rises quickly enough! Tmo just got a minor permit approved (upgrade to mi mo) and it took well over a year (entered 8-29-12). Permit fees are pretty low though,  perhaps charging more would give them more resources since they got slashed in 2007/ 8 .

Link to comment
Share on other sites

I get what you're saying. And I pretty much agree. However, please be a little more careful how you post critical Sprint comments. Someone may mistake that for a rant, which would be against the S4GRU posting guidelines.

 

Robert via Nexus 5 using Tapatalk

If someone mistakes that as a rant I'll give them the dictionary definition of a rant :P

Link to comment
Share on other sites

If someone mistakes that as a rant I'll give them the dictionary definition of a rant :P

Please.

 

Robert via Nexus 5 using Tapatalk

 

 

Link to comment
Share on other sites

You know they approve they double digit pay rises quickly enough! Tmo just got a minor permit approved (upgrade to mi mo) and it took well over a year (entered 8-29-12). Permit fees are pretty low though,  perhaps charging more would give them more resources since they got slashed in 2007/ 8 .

Perhaps bribing the county of maui and the state of Hawaii will work, idunno..

Link to comment
Share on other sites

40 new Markets were announced today. Obviously Oahu wasn't one of them. I did wake up this morning however to a text saying that the network would be largely completed in my area in the following month, but it appears most people don't believe this is even true, so thats exciting and then not exciting. haha

Link to comment
Share on other sites

40 new Markets were announced today. Obviously Oahu wasn't one of them. I did wake up this morning however to a text saying that the network would be largely completed in my area in the following month, but it appears most people don't believe this is even true, so thats exciting and then not exciting. haha

 

The text went out to pretty much everyone, even people who don't live in Sprint coverage areas anymore, so I wouldn't read much into it. Sorry :/

Link to comment
Share on other sites

  • 2 weeks later...

Just a spoiler for those that live on west Maui side, Lahaina shores is getting the lte tower upgrade slowly but surely. The solar company I'm working for is installing panels up there so by chance I seen some guys upgrading radio equipment up top. They said it will be a few days to install (give or take abit due to the rain) and a month of testing before it goes live. I'm finally stoked .... (Sorry Oahu guys)

  • Like 1
Link to comment
Share on other sites

My brother in law said his friend picked up LTE at a Starbucks near HNL. I'm going to Hickam to do a job on the 18th, I'll see if the Pearl Harbor iden conversion tower is live

 

Sent from my SM-N900P using Tapatalk

 

Link to comment
Share on other sites

Just a spoiler for those that live on west Maui side, Lahaina shores is getting the lte tower upgrade slowly but surely. The solar company I'm working for is installing panels up there so by chance I seen some guys upgrading radio equipment up top. They said it will be a few days to install (give or take abit due to the rain) and a month of testing before it goes live. I'm finally stoked .... (Sorry Oahu guys)

 

Is there any chance it was AT&T and not Sprint as AT&T are the only ones with a recent ish permit in the system for that TMK \ Address or their normal Designer \ Engineer? Although I wouldn't be shocked if the system was borked.

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.


  • large.unreadcontent.png.6ef00db54e758d06

  • gallery_1_23_9202.png

  • Posts

    • Was in Red Hook again and I swear there are more Link5G sites as there are Verizon, T-Mobile, and AT&T small cells combined in the entire neighborhood. It seemed like every other street I turned down had one installed. Hopefully carriers will start hopping on them soon. Seems like a lot of effort to go through for no one to use them.  — — — — — T-Mobile converted the Sprint site on top of NYU Langone Brooklyn in Sunset Park. I first mapped one sector of it back in November 2023 but I thought it was a small cell so I never pinned it but I ran into another sector today which caught me off guard. I'm unable to find a permit for the conversion so it's definitely a surprise. There's another T-Mobile site 1 block away that T-Mobile initially installed back in 2019 so I'm kinda surprised they're keeping both considering the Sprint conversion is on a much taller building and could potentially provide much better coverage to the entire area.  — — — — — The old permit expired for this site without any work being done but a new permit was just approved a few days ago for a T-Mobile site at this address. Description mentions 3 antennas with 2 RRUs per sector. My guess is they're doing something similar to what they did at 360 Furman St in Brooklyn where they broadcast Band 2/66 and n25/41 from one antenna. It's a bit of a downgrade considering the site it's replacing was a full build with Ericsson 6449s. 
    • Still not seeing any ULS postings for pending T-Mobile UScellular merger in Dane county Wisconsin.
    • Came across another Crown Castle Solutions multi-tenant oDAS node in Brooklyn. Located at 40.7002286, -73.9612666. Nothing on T-Mobile or AT&T so I'm assuming these are all Verizon nodes that Crown Castle is anticipating another carrier will hop on down the line.