The 3 months is not a delay in NYC launch from 12/31 to 3/31. It's an overall total sites count. Sprint has been advertising to investors all year that they would have 12,000 sites complete before the end of the year. This is their way of getting themselves off the hook and saying they are one quarter behind in site counts.
By our best assessment, NYC launch is 30-45 days behind the initial baseline schedule. It would be as bad as 90 days, but now that Sprint is focusing on soft launches, that is still conceivable by December 31st.
Robert via Nexus 7 using Forum Runner