Jump to content

Network Vision/LTE - Arkansas Market (Little Rock/Ft. Smith/NW Arkansas)


smj9

Recommended Posts

In recent days, I saw some activity (workers installing new cabinets) at a tower just off I-40 in Pope County, Arkansas; this afternoon, I drove by the tower and saw what appear to be new (Ericsson) NV cabinets installed alongside Sprint's old Nortel cabinets:

 

http://i.imgur.com/ZstTX.jpg

 

The new cabinets are behind the older, bulkier cabinets. Sorry about the angle of the photo.

 

It doesn't appear that work (antennas/RRUs) has started on the tower yet - I'll be watching for those changes.

Edited by smj9
  • Like 2
Link to comment
Share on other sites

In recent days, I saw some activity (workers installing new cabinets) at a tower just off I-40 in Pope County, Arkansas; this afternoon, I drove by the tower and saw what appear to be new (Ericsson) NV cabinets installed alongside Sprint's old Nortel cabinets:

 

http://i.imgur.com/ZstTX.jpg

 

The new cabinets are behind the older, bulkier cabinets. Sorry about the angle of the photo.

 

It doesn't appear that work (antennas/RRUs) has started on the tower yet - I'll be watching for those changes.

 

Very possible. Keep your eyes out for panel work. Thanks for the photo and starting the thread.

 

Robert

Link to comment
Share on other sites

I just uploaded the first 5 sites as In Progress in the Arkansas market over in the NV Sites Complete maps. They are in the Pine Bluff and El Dorado area. These sites are actually accepted as complete with 3G Network Vision upgrades and will appear in next week's update.

 

Robert

  • Like 2
Link to comment
Share on other sites

I just uploaded the first 5 sites as In Progress in the Arkansas market over in the NV Sites Complete maps. They are in the Pine Bluff and El Dorado area. These sites are actually accepted as complete with 3G Network Vision upgrades and will appear in next week's update.

 

Robert

Do you know when Little Rock will start to see some work? Any info would be nice. Also I wonder with this last snow storm we got if its going to cause any delays.
Link to comment
Share on other sites

Do you know when Little Rock will start to see some work? Any info would be nice. Also I wonder with this last snow storm we got if its going to cause any delays.

 

Specifically? No. But probably in the next 30-60 days.

 

Robert via Samsung Note II via Tapatalk

 

 

  • Like 1
Link to comment
Share on other sites

  • 2 months later...

Looks like Sprint has started pulling permits in Arkansas (I'm not 100% sure that the ones pulled in January are Sprint's - there's no contractor/owner name listed; however, the costs match the Sprint permit from February):

 

 

se9TPoU.jpg

 

OBw1BX5.jpg

Edit: I checked both addresses from the January list in Google Maps Street View - both are cell sites. However, there is a possibility that they are AT&T's, as AT&T is building out its LTE network in the same area right now (I was actually trying to locate AT&T permits - most of those have been for $47,000).

 

5006 West Main: http://bit.ly/ZFcyLE

 

907 East 3rd: http://bit.ly/13rH4xJ

Edited by smj9
  • Like 1
Link to comment
Share on other sites

  • 4 weeks later...

Any update as far when Little Rock will start to see some LTE sites go live? Went to Memphis the other day and got use LTE for the first time. Now I know how it feels to be back on 3G after LTE and its like a slap in the face. lol

Link to comment
Share on other sites

Any update as far when Little Rock will start to see some LTE sites go live? Went to Memphis the other day and got use LTE for the first time. Now I know how it feels to be back on 3G after LTE and its like a slap in the face. lol

 

I had some excellent LTE in Memphis a few months back,.... as far as when a site goes live nobody can tell for sure. Once it's been accepted for 3G I believe it could go live at any time...this could still take a while. But knowing that its close is semi-comforting. I can almost taste the LTE goodness now!

Link to comment
Share on other sites

  • 1 month later...

Just saw some guys up on the tower not far from my house.  Verizon is located at the top and AT&T is located at the bottom.  AT&T just installed new panels and RRUs at the bottom - I'm ready for AT&T LTE to be available!  Now, after seeing the work today, I'm wondering whether Sprint will switch on LTE first.

 

y5Ug64U.jpg

vmdPCrY.jpg

  • Like 1
Link to comment
Share on other sites

Arkansas appears to be in a position for rapid Lte deployment. 3G is complete across the state, its just a matter of installing 4G equipment on the site, which is the quickest piece of the puzzle.

 

Most of the Arkansas sites that have been accepted so far are GMO, which means they probably won't be seeing LTE soon. I don't believe the full build sites have begun yet. Once those start, you will see LTE popping up, but not likely from any of the sites that are already 3G accepted.

 

Sent from my HTC ONE

 

 

  • Like 1
Link to comment
Share on other sites

Most of the Arkansas sites that have been accepted so far are GMO, which means they probably won't be seeing LTE soon. I don't believe the full build sites have begun yet. Once those start, you will see LTE popping up, but not likely from any of the sites that are already 3G accepted.

 

Sent from my HTC ONE

 

Well, i retract my statement then.  Sorry Arkansas folks :blush:

  • Like 1
Link to comment
Share on other sites

Well, i retract my statement then.  Sorry Arkansas folks :blush:

A lot of the 3G you see across the south from Ericsson is GMOs. Apparently they're knocking them out of the way before they start on full builds. At least in markets that don't have any full builds yet (East&West Texas, Louisiana, Gulf Coast, Alabama [first full build this week I think], Mississippi, you get the point.) It's hard to tell the difference, so it is easy to get that confused with what AL is doing!

  • Like 2
Link to comment
Share on other sites

Ehh... should have looked at the pictures!

 

That's a full build Arkansas Sprint NV site! Looks like full build sites are underway in Arkansas, which means LTE is not too far away! It will be spotty at first (See St. Louis, Las Vegas) but will fill in over time.

  • Like 1
Link to comment
Share on other sites

I thought that video was showing a tower being upgraded in Jonesboro because that's a part of the Memphis market isn't it? But still has the LR****** (site ID). At least that's what I am thinking. Correct me if I'm wrong. But that's just my guess

 

Sent from my EVO using Tapatalk 2

 

 

Link to comment
Share on other sites

There is a video that someone posted on this forum by tower crew personnel of a full build in Little Rock.

 

I'm pretty sure that was in Jonesboro, AR. Since it's a part of the Memphis market. Just has the LR in the site ID.
  • Like 1
Link to comment
Share on other sites

There is a video that someone posted on this forum by tower crew personnel of a full build in Little Rock. 

 

 

I'm pretty sure that was in Jonesboro, AR. Since it's a part of the Memphis market. Just has the LR in the site ID.

Ok yeah the site your talking about is in Jonesboro, AR. I just found the link to the post http://s4gru.com/index.php?/topic/3581-tower-install-video/?hl=%2Btower+%2Bvideo then I noted down the site # and then I went back to the NV sites complete map and  found that same site # and it was showing that 3G has been accepted. 

  • Like 1
Link to comment
Share on other sites

  • 4 weeks later...

Just thought id mention that I noticed some 4G in between Benton and Bryant. Oh and im not sure if it was a sprint tower, but I saw someone working on a tower near I-430 in Little Rock. Some work is finally going on. And it looks like me and someone else mapped it on sensorly. Can't wait for whats coming..  :D  :D

Link to comment
Share on other sites

Here is a speed test from Van Buren, AR that has an active LTE tower. I also used sensorly at the same time to track the signal as well.

 

Sent from my HTCONE using Tapatalk 4 Beta

 

post-1027-13716075500534_thumb.jpg

  • Like 1
Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.


  • large.unreadcontent.png.6ef00db54e758d06

  • gallery_1_23_9202.png

  • Similar Content

  • Posts

    • Since this is kind of the general chat thread, I have to share this humorous story (at least it is to me): Since around February/March of this year, my S22U has been an absolute pain to charge. USB-C cables would immediately fall out and it progressively got worse and worse until it often took me a number of minutes to get the angle of the cable juuuussst right to get charging to occur at all (not exaggerating). The connection was so weak that even walking heavily could cause the cable to disconnect. I tried cleaning out the port with a stable, a paperclip, etc. Some dust/lint/dirt came out but the connection didn't improve one bit. Needless to say, this was a MONSTER headache and had me hating this phone. I just didn't have the finances right now for a replacement.  Which brings us to the night before last. I am angry as hell because I had spent five minutes trying to get this phone to charge and failed. I am looking in the port and I notice it doesn't look right. The walls look rough and, using a staple, the back and walls feel REALLY rough and very hard. I get some lint/dust out with the staple and it improves charging in the sense I can get it to charge but it doesn't remove any of the hard stuff. It's late and it's charging, so that's enough for now. I decide it's time to see if that hard stuff is part of the connector or not. More aggressive methods are needed! I work in a biochem lab and we have a lot of different sizes of disposable needles available. So, yesterday morning, while in the lab I grab a few different sizes of needles between 26AWG and 31 AWG. When I got home, I got to work and start probing the connector with the 26 AWG and 31 AWG needle. The stuff feels extremely hard, almost like it was part of the connector, but a bit does break off. Under examination of the bit, it's almost sandy with dust/lint embedded in it. It's not part of the connector but instead some sort of rock-hard crap! That's when I remember that I had done some rock hounding at the end of last year and in January. This involved lots of digging in very sandy/dusty soils; soils which bare more than a passing resemblance to the crap in the connector. We have our answer, this debris is basically compacted/cemented rock dust. Over time, moisture in the area combined with the compression from inserting the USB-C connector had turned it into cement. I start going nuts chiseling away at it with the 26 AWG needle. After about 5-10 minutes of constant chiseling and scraping with the 26AWG and 31AWG needles, I see the first signs of metal at the back of the connector. So it is metal around the outsides! Another 5 minutes of work and I have scraped away pretty much all of the crap in the connector. A few finishing passes with the 31AWG needle, a blast of compressed air, and it is time to see if this helped any. I plug my regular USB-C cable and holy crap it clicks into place; it hasn't done that since February! I pick up the phone and the cable has actually latched! The connector works pretty much like it did over a year ago, it's almost like having a brand new phone!
    • That's odd, they are usually almost lock step with TMO. I forgot to mention this also includes the September Security Update.
    • 417.55 MB September security update just downloaded here for S24+ unlocked   Edit:  after Sept security update install, checked and found a 13MB GP System update as well.  Still showing August 1st there however. 
    • T-Mobile is selling the rest of the 3.45GHz spectrum to Columbia Capital.  
    • Still nothing for my AT&T and Visible phones.
  • Recently Browsing

    • No registered users viewing this page.
×
×
  • Create New...