I saw some workers up there about a week and a half ago.  They took down two legacy antennas and left the new antenna and RRUs as they have other sites that were updated. 

Link to comment
Share on other sites

  • 1 month later...

Looking at Tampa permits - looks like the site at HCC (Permit: BLD-15-0439113) should be underway and the DAS at RayJay (Permit: BTR-15-0441423) has passed City inspection as of 8/18. Exciting to see NV1.0 finally edge ever closer to a close in Tampa!

Link to comment
Share on other sites

  • 4 weeks later...
  • 4 weeks later...
  • 2 weeks later...
  • 4 weeks later...

Anyone notice that network.sprint.com is no longer up? You can't see upgrades any more on the Sprint site.

 

Sent from my XT1254 using Tapatalk

Yep, has been gone since early October.

 

Using Tapatalk on Note 8.0

Link to comment
Share on other sites

I was there on Nov 14, 2015 this was done over on Dale mabry hwy and I275.  I was on Dale mabry when I did the speed test. 

 

This is the fast one i have gotten in the Tampa area.

 

Screenshot_2015-11-14-16-10-01.png

 

later,

 

John

 

 

 

  • Like 1
Link to comment
Share on other sites

  • 3 months later...
  • 4 weeks later...
  • 3 months later...

Mobilitie has filed for permits with the City of Tampa. Looks like the process started on May 31st and they have been going back and forth for a while. Tampa's permitting system is a little wonky, but very detailed.

 

Go here: https://aca.tampagov.net/citizenaccess/ and search for either Mobilitie or "ROW-16-0000643"

 

If you click 'Application Information Table' you'll get more detail to work locations and specific site plans are posted at the bottom of the page under 'Attachments.'

 

Exciting to see more small cell work underway in my hometown.

  • Like 4
Link to comment
Share on other sites

  • 2 weeks later...
  • 2 months later...
  • 3 weeks later...

So has Mobilitie built any small cell at all in Tampa?

 

 

Sent from my iPhone using Tapatalk

 

Not under their current agreement. Sprint did build some small cells in Channelside and around the Ice Palace/Forum/Amelie Arena for the 2012 GOP convention. I tried to get pictures of them once, but felt a little awkward.

Link to comment
Share on other sites

  • 2 weeks later...
  • 1 month later...

Three new permits filed for adding B41 equipment to existing towers. Looks like things are moving again.

 

Whoa.PNG

 

Search for them here: https://aca.tampagov.net/citizenaccess/

About time. Tampa is far behind Orlando and Miami in band 42 deployment and Jacksonville is really far behind.
  • Like 1
Link to comment
Share on other sites

About time. Tampa is far behind Orlando and Miami in band 42 deployment and Jacksonville is really far behind.

 

I didn't realize Tampa was that far behind, the network seems pretty solid within the city core. The airport has improved, but could still use a DAS.

Link to comment
Share on other sites

  • 2 weeks later...

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.


  • large.unreadcontent.png.6ef00db54e758d06

  • gallery_1_23_9202.png

  • Posts

    • Probably a lot of Midwest towers. Slight bias since Nebraska is a weird market, but there are tons of USCC sites that T-Mobile isn't yet co-located on. Think a similar situation in Iowa, Wisconsin, and Missouri. But some other markets, like yours, probably don't have that issue!
    • Sticky Customers - YES, and leave them flip to the T-Mobile PLMN when needed and they will be even more likely to Stick.
    • It seems to me that if the goal is to improve rural, the US Cellular buy-out would get them only part of the way there, considering there are plenty of rural areas that US Cellular does not serve.  But I also have a hard time reading it the way I think that article is, that the cost of this deal comes straight out of the $9 billion.  I mean, they're getting spectrum for their existing operations in US Cellular markets, including places that I wouldn't call rural.  (Roanoke, VA is the 9th largest city in the state, for example.)  It seems like some of it should be allocated to rural expansion, but certainly not the whole purchase price. There's also something to be said for getting the customer base of potentially sticky customers who have been used to US Cellular being the only game in town for potentially decades. - Trip
    • T-Mobile has stated 15% of their sites don't have 5g triband. In WV I know WISPs had a lot of 2.5GHz, but T-Mobile was trying to buy as much as possible. More rural FWA would be a big selling point that might overcome any soft bandwidth cap slight overages. Especially since UScellular likely started offering it on c-band.
  • Recently Browsing

    • No registered users viewing this page.
×
×
  • Create New...