Network Vision/LTE Deployment Running List


Recommended Posts

Long Island

Status:  LTE Launched/NV Upgrades Continuing
NV Sites Accepted = 85%

LTE Sites Accepted = 76%
LTE Launched = April 29, 2014

Original Scheduled Completion = September 2013
Current Production Rate Completion = December 2015

  • Like 10
Link to comment
Share on other sites

Memphis

Status:  LTE Launched/NV Upgrades Complete/Difficult Sites Remaining
NV Sites Accepted = 100%

LTE Sites Accepted = 99%
LTE Launched = April 18, 2013

Original Scheduled Completion = February 2013
Complete = May 2014

  • Like 10
Link to comment
Share on other sites

  • 9 months later...

Miami/West Palm

Status:  LTE Launched/NV Upgrades Completing
NV Sites Accepted = 92%

LTE Sites Accepted = 90%
LTE Launched = June 17, 2013 (West Palm Beach launched 4/18/2013)

Original Scheduled Completion = February 2013
Current Production Rate Completion = September 2015

  • Like 19
Link to comment
Share on other sites

  • 1 month later...

Minnesota

Status:  LTE Launched/NV Upgrades Complete/Difficult Sites Remaining
NV Sites Accepted = 100%

LTE Sites Accepted = 90%
LTE Launched = April 29, 2014 (LaCrosse, WI launched 3/2013, Mankato 4/2013, St. Cloud 6/2013)

Original Scheduled Completion = September 2013
Complete = August 2014

  • Like 12
Link to comment
Share on other sites

Nashville

Status:  LTE Launched/NV Substantially Complete/Difficult Sites Remaining
NV Sites Accepted = 99%

LTE Sites Accepted = 98%
LTE Launched = July 30, 2013 (Columbia launched 1/2013, Greeneville/Tullahoma 4/2013, Clarksville/Kingsport 6/2013)

Original Scheduled Completion = February 2013
Substantial Completion = September 2014

  • Like 5
Link to comment
Share on other sites

New Orleans

Status:  LTE Launched/NV Upgrades Completing
NV Sites Accepted = 97%

LTE Sites Accepted = 95%
LTE Launched = June 17, 2013 (North Shore launched 3/4/2013)

Original Scheduled Completion = May 2013
Current Production Rate Completion = September 2015

  • Like 2
Link to comment
Share on other sites

Norfolk (Hampton Roads/Tidewater)

Status:  LTE Launched/NV Upgrades Substantially Complete/Difficult Sites Remaining
NV Sites Accepted = 98%

LTE Sites Accepted = 83%
LTE Launched = April 18, 2013

Original Scheduled Completion = February 2013
Substantial Completion = May 2014

Link to comment
Share on other sites

Northern Jersey

Status:  LTE Launched/NV Upgrades Completing
NV Sites Accepted = 94%

LTE Sites Accepted = 70%
LTE Launched = April 29, 2014

Original Scheduled Completion = September 2013
Current Production Rate Completion = July 2015

  • Like 6
Link to comment
Share on other sites

Orange County (California)

Status:  LTE Launched/NV Upgrades Continuing
NV Sites Accepted = 90%

LTE Sites Accepted = 81%

LTE Launched = October 31, 2013

Original Scheduled Completion = August 2013
Current Production Rate Completion = July 2015

  • Like 9
Link to comment
Share on other sites

Oregon/SW Washington

Status:  LTE Launched/NV Upgrades Substantially Complete/Difficult Sites Remaining
NV Sites Accepted = 99%

LTE Sites Accepted = 80%
LTE Launched = July 30, 2013 (Longview/Kelso launched 6/2013)

Original Scheduled Completion = September 2013
Substantial Completion = April 2014

  • Like 1
Link to comment
Share on other sites

Orlando

Status:  LTE Launched/NV Upgrades Completing
NV Sites Accepted = 95%

LTE Sites Accepted = 91%
LTE Launched = December 15, 2013 (Melbourne/Palm Bay & Port St. Lucie launched 4/2013, Daytona Beach/Palm Coast launched 7/2013, Lakeland/Winter Haven 10/2013)

Original Scheduled Completion = May 2013
Current Production Rate Completion = August 2015

  • Like 18
Link to comment
Share on other sites

Philadelphia Metro

Status:  LTE Launched/NV Upgrades Substantially Complete/Difficult Sites Remaining
NV Sites Accepted = 98%

LTE Sites Accepted = 84%
LTE Launched = July 30, 2013

Original Scheduled Completion = July 2013
Substantial Completion = October 2014

  • Like 3
Link to comment
Share on other sites

PR/VI

Status:  LTE Launched/NV Upgrades Complete/LTE Deployment Continuing
NV Sites Accepted = 100%

LTE Sites Accepted = 93%
LTE Launched = March 4, 2013 (Southern PR launched 12/18/2012, 
Western PR 1/28/2013)

Original Scheduled Completion = May 2013
Complete = August 2013

  • Like 4
Link to comment
Share on other sites

Raleigh/Durham

Status:  LTE Launched/NV Upgrades Substantially Complete/LTE Deployment Continues
NV Sites Accepted = 99%

LTE Sites Accepted = 93%
LTE Launched = June 17, 2013

Original Scheduled Completion = August 2013
Substantial Completion = April 2014

  • Like 5
Link to comment
Share on other sites

Riverside/San Bernardino

Status:  LTE Launched/NV Upgrades Completing
NV Sites Accepted = 93%

LTE Sites Accepted = 79%
LTE Launched = June 23, 2014

Original Scheduled Completion = October 2013
Current Production Rate Completion = August 2015

  • Like 8
Link to comment
Share on other sites

San Diego

Status:  LTE Launched/NV Upgrades Continuing
NV Sites Accepted = 86%

LTE Sites Accepted = 77%
LTE Launched = December 15, 2013

Original Scheduled Completion = May 2013
Current Production Rate Completion = August 2015

  • Like 16
Link to comment
Share on other sites

Shentel (Sprint Affiliate)

Status:  LTE Launched/NV Upgrades Complete
NV Sites Accepted = 100%

LTE Sites Accepted = 98%
LTE Launched = November 26, 2012

Original Scheduled Completion = December 2013
Complete = November 2013

  • Like 2
Link to comment
Share on other sites

South Bay (San Jose/Monterey Bay)

Status:  LTE Launched/NV Upgrades Substantially Complete/Difficult Sites Remaining
NV Sites Accepted = 98%

LTE Sites Accepted = 87%
LTE Launched = July 23, 2014 (Salinas/Watsonville/Monterey launched 7/2013)

Original Scheduled Completion = August 2013
Substantial Completion = July 2014

  • Like 3
Link to comment
Share on other sites

Southern Connecticut

Status:  LTE Launched/NV Upgrades Substantially Complete/Difficult Sites Remaining

NV Sites Accepted = 99%

LTE Sites Accepted = 93%
LTE Launched = October 2013

Original Scheduled Completion = August 2013
Substantial Completion = July 2014

  • Like 6
Link to comment
Share on other sites

South West Florida

Status:  LTE Launched/NV Substantially Complete/Difficult Sites Remaining
NV Sites Accepted = 92%

LTE Sites Accepted = 92%
LTE Launched = March 17, 2014 (Port Charlotte/Punta Gorda launched 7/2013, Cape Coral/Fort Myers/Naples launched 10/2013, Marco Island 12/2013)

Original Scheduled Completion = March 2013
Substantial Completion = October 2014

  • Like 2
Link to comment
Share on other sites

Tampa

Status:  LTE Launched/NV Substantially Complete/Difficult Sites Remaining
NV Sites Accepted = 96%

LTE Sites Accepted = 95%
LTE Launched = July 30, 2013

Original Scheduled Completion = March 2013
Substantial Completion = August 2014

  • Like 3
Link to comment
Share on other sites

West Michigan
Status:  LTE Launched/NV Upgrades Complete/LTE Deployment Continues
NV Sites Accepted = 100%

LTE Sites Accepted = 94%
LTE Launched = July 30, 2013 (Lansing/Benton Harbor launched 6/2013)

Original Scheduled Completion = August 2013
Completion = January 2014

  • Like 10
Link to comment
Share on other sites

West Washington

Status:  LTE Launched/NV Upgrades Substantially Complete/Difficult Sites Remaining

NV Sites Accepted = 99%

LTE Sites Accepted = 82%
LTE Launched = June 23, 2014 (Centralia/Chehalis launched 7/2013, Bremerton/Silverdale 12/2013, Tacoma/Olympia 1/2014, Bellingham/Blaine 2/2014)

Original Scheduled Completion = September 2013
Substantial Completion = October 2014

  • Like 10
Link to comment
Share on other sites

Central Illinois

Status:  LTE Launched/NV Upgrades Complete/LTE Deployment Continues
NV Sites Accepted = 100%

LTE Sites Accepted = 73%
LTE Launched = September 9, 2014 (Charleston/Mattoon launched 2/2014, Peoria 3/2014, Bloomington/Normal 6/2014)

Original Scheduled Completion = Q4 2013
Complete = January 2014

  • Like 1
Link to comment
Share on other sites

Central Iowa
Status:  LTE Launched/NV Upgrades Complete/LTE Deployment Continues
NV Sites Accepted = 100%

LTE Sites Accepted = 77%
LTE Launched = April 29, 2014 (Mason City launched 3/17/2014)

Original Scheduled Completion = Q1 2014
Complete = January 2014

  • Like 4
Link to comment
Share on other sites

Guest
This topic is now closed to further replies.

  • large.unreadcontent.png.6ef00db54e758d06

  • gallery_1_23_9202.png

  • Similar Content

  • Posts

    • This has been approved.. https://www.cnet.com/tech/mobile/fcc-approves-t-mobiles-deal-to-purchase-mint-mobile/  
    • In the conference call they had two question on additional spectrum. One was the 800 spectrum. They are not certain what will happen, thus have not really put it into their plans either way (sale or no sale). They do have a reserve level. Nationwide 800Mhz is seen as great for new technologies which I presume is IOT or 5g slices.  T-Mobile did not bite on use of their c-band or DOD.  mmWave rapidly approaching deadlines not mentioned at all. FWA brushes on this as it deals with underutilized spectrum on a sector by sector basis.  They are willing to take more money to allow FWA to be mobile (think RV or camping). Unsure if this represents a higher priority, for example, FWA Mobile in RVs in Walmart parking lots working where mobile phones need all the capacity. In terms of FWA capacity, their offload strategy is fiber through joint ventures where T-Mobile does the marketing, sales, and customer support while the fiber company does the network planning and installation.  50%-50% financial split not being consolidated into their books. I think discussion of other spectrum would have diluted the fiber joint venture discussion. They do have a fund which one use is to purchase new spectrum. Sale of the 800Mhz would go into this. It should be noted that they continue to buy 2.5Ghz spectrum from schools etc to replace leases. They will have a conference this fall  to update their overall strategies. Other notes from the call are 75% of the phones on the network are 5g. About 85% of their sites have n41, n25, and n71, 90% 5g.  93% of traffic is on midband.  SA is also adding to their performance advantage, which they figure is still ahead of other carriers by two years. It took two weeks to put the auction 108 spectrum to use at their existing sites. Mention was also made that their site spacing was designed for midrange thus no gaps in n41 coverage, while competitors was designed for lowband thus toggles back and forth for n77 also with its shorter range.  
    • The manual network selection sounds like it isn't always scanning NR, hence Dish not showing up. Your easiest way to force Dish is going to be forcing the phone into NR-only mode (*#*#4636#*#* menu?), since rainbow sims don't support SA on T-Mobile.
    • "The company’s unique multi-layer approach to 5G, with dedicated standalone 5G deployed nationwide across 600MHz, 1.9GHz, and 2.5GHz delivers customers a consistently strong experience, with 85% of 5G traffic on sites with all three spectrum bands deployed." Meanwhile they are very close to a construction deadline June 1 for 850Mhz of mmWave in most of Ohio covering 27500-28350Mhz expiring 6/8/2028. No reported sightings.  Buildout notice issue sent by FCC in March 5, 2024 https://wireless2.fcc.gov/UlsApp/letterPdf/LetterPdfController?licId=4019733&letterVersionId=178&autoLetterId=13060705&letterCode=CR&radioServiceCode=UU&op=LetterPdf&licSide=Y&archive=null&letterTo=L  No soecific permits seen in a quick check of Columbus. They also have an additional 200Mhz covering at 24350-25450 Mhz and 24950-25050Mhz with no buildout date expiring 12/11/2029.
    • T-Mobile Delivers Industry-Leading Customer, Service Revenue and Profitability Growth in Q1 2024, and Raises 2024 Guidance https://www.t-mobile.com/news/business/t-mobile-q1-2024-earnings — — — — — I find it funny that when they talk about their spectrum layers they're saying n71, n25, and n41. They're completely avoiding talking about mmWave.