I know you guys are dying in the Tampa market, because you have seen sites with panels installed 30-45 days ago. But I have something that you may appreciate. I live next to a Sprint/Verizon/Tmo/Cricket site here in New Mexico. Verizon installed new microwave radomes in January, and LTE panels in February 2012. It just went live last Friday morning.

 

So even though we get worked up about Sprint LTE not going live right after panel install, we have to keep in perspective how much in advance Sprint is allowing us to connect to the new network. It is kind of unprecedented to allow them to go live as each site is ready. I really appreciate it.

 

Robert

Link to comment
Share on other sites

I know you guys are dying in the Tampa market, because you have seen sites with panels installed 30-45 days ago. But I have something that you may appreciate. I live next to a Sprint/Verizon/Tmo/Cricket site here in New Mexico. Verizon installed new microwave radomes in January, and LTE panels in February 2012. It just went live last Friday morning.

 

So even though we get worked up about Sprint LTE not going live right after panel install, we have to keep in perspective how much in advance Sprint is allowing us to connect to the new network. It is kind of unprecedented to allow them to go live as each site is ready. I really appreciate it.

 

Robert

 

And on that note I will now shut up lol thanks Robert :D patience is truly a virtue.. That I don't have unfortunately.

 

Sent from my EVO using Tapatalk 2

 

 

  • Like 1
Link to comment
Share on other sites

Has anyone confirmed if the tower off 275 near the 4th st exit is sprint or NV for that matter?

If you are talking about the monopole at the very end of 4th st as you get on to 275N then no. I passed there on Sat twice and didnt see anything that looked like it.
Link to comment
Share on other sites

I work in South Tampa. 3G speeds here are super fast. I can watch Netflix and YouTube without it pausing at all to buffer - something I can't do in other areas. I can see a tower from the parking lot - It looks like it is somewhere on South Dale Mabry, south of Gandy Blvd. Is it possible I have LTE and I just don't know it!

 

 

- George

 

Sent from my iPhone 5 using Tapatalk.

Link to comment
Share on other sites

When u look its always there. When I first noticed it I looked at it constantly and it was there sometimes other times not but I could toggle and it would be back. I don't look now nearly as I used to but between the speed tests checking for backhaul work and toggling looking for LTE I feel pretty sure saying I have it all the time.

 

Sent from my EVO using Tapatalk 2

 

 

Link to comment
Share on other sites

Keep in mind that the tower crew will have 3-4 on site, there maybe at least 2 electricians and possibly someone from Sprint and Ericsson.. You may see a county inspector, and somebody to build the slab.. Gets crowded

 

Sent from my EVO using Tapatalk 2

 

 

Link to comment
Share on other sites

So was crusing back on some of the posts, looks like early Nov we started seeing LTE panels up, and likely sometime in Oct is when some were completed but were just noticed by us. I feel there has to be one, at the very least just one site someplace in this market that is operating. I was keeping up with the Jacksonville thread but I'm so jealous now I can't bear to read it anymore, but when I was keeping up with them I'm not sure any of them had seen any panels before one of Roberts updates told them LTE was live at a site.

 

I have 2 questions. Do backhaul always involve digging? and what does bringing the core on line in a market consist of.

  • Like 1
Link to comment
Share on other sites

Are any of you guys over in Clearwater? I work that way so I can check but there are 8 permits pulled there by the same company.. I'm gonna checkout Ruth Eckard at lunch to see if anything interesting is going on over there. I'm so freaking bored

 

Sent from my EVO using Tapatalk 2

 

 

Link to comment
Share on other sites

Are any of you guys up in New Port Richey/Oldsmar area? New Tech has 11 permits pulled on the Pinellas County website and of those I can confirm that 4 have panels up. The other ones I'm pretty sure I can look at but there are two that are on East Lake Rd which isn't far for me, but if one of you is closer to the area you might be able to take a look

Link to comment
Share on other sites

Are any of you guys up in New Port Richey/Oldsmar area? New Tech has 11 permits pulled on the Pinellas County website and of those I can confirm that 4 have panels up. The other ones I'm pretty sure I can look at but there are two that are on East Lake Rd which isn't far for me, but if one of you is closer to the area you might be able to take a look

 

is it the pinellas county permit site you got a link?

Edited by TuX
Link to comment
Share on other sites

It's Pinellas county. On Page 23 of this thread I listed the contractors who have pulled permits for Sprint work. The top license number on that list is New Tech. Copy that number an taken it to the permit site if Pinellas county and do a search for them by license number

 

Sent from my EVO using Tapatalk 2

 

 

Link to comment
Share on other sites

It's Pinellas county. On Page 23 of this thread I listed the contractors who have pulled permits for Sprint work. The top license number on that list is New Tech. Copy that number an taken it to the permit site if Pinellas county and do a search for them by license number

 

Sent from my EVO using Tapatalk 2

 

wow you sir are awesome!

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.


  • large.unreadcontent.png.6ef00db54e758d06

  • gallery_1_23_9202.png

  • Posts

    • You could also just sign up for Project Genesis directly, $400 for the moto edge+ 2023 and $25/month for service.
    • Your referring to the $25.00 a month Infinite Unlimited plan?  I don't see any other plans on there even cheaper than that on their website.  I was looking at the Motorola 2023 Edge fwiw as well for $10.00 a month. 
    • A heavy n41 overlay as an acquisition condition would be a win for customers, and eventually a win for T-Mobile as that might be enough to preclude VZW/AT&T adding C-Band for FWA due to spreading the market too thinly (which means T-Mobile would just have local WISPs/wireline ISPs as competition). USCC spacing (which is likely for contiguous 700 MHz LTE coverage in rural areas) isn't going to be enough for contiguous n41 anyway, and I doubt they'll densify enough to get there.
    • Boost Infinite with a rainbow SIM (you can get it SIM-only) is the cheapest way, at $25/mo, to my knowledge; the cheaper Boost Mobile plans don't run on Dish native. Check Phonescoop for n70 support on a given phone; the Moto G 5G from last year may be the cheapest unlocked phone with n70 though data speeds aren't as good as something with an X70 or better modem.
    • Continuing the USCC discussion, if T-Mobile does a full equipment swap at all of USCC's sites, which they probably will for vendor consistency, and if they include 2.5 on all of those sites, which they probably will as they definitely have economies of scale on the base stations, that'll represent a massive capacity increase in those areas over what USCC had, and maybe a coverage increase since n71 will get deployed everywhere and B71 will get deployed any time T-Mobile has at least 25x25, and maybe where they have 20x20. Assuming this deal goes through (I'm betting it does), I figure I'll see contiguous coverage in the area of southern IL where I was attempting to roam on USCC the last time I was there, though it might be late next year before that switchover happens.
  • Recently Browsing

    • No registered users viewing this page.
×
×
  • Create New...