Everything posted by Nirav1983

  1. there were 6 sties (OK03SW054, OK03SW110, OK03SW619, TU13XC458,TU54XC301, TU60XC495 ) LTE have been integrated last weekend all around Oklahoma...
  2. Site #TU03XC329 (36.326389 -95.595556, claremore, OK) LTE has been integrated ! Awaits Sprint Approval!!
  3. Update !!! TU54XC412(35.930556, -95.891389)Tulsa area, OK LTE has been integrated today..Sent sprint for Approval !!!
  4. Kool !!! In next 30-40 days there will be bunch of sites will be ready LTE......Work in progress many sites all around Springfield......
  5. ST03RW434 (37.761667 -92.525833, Stoutland, MO) LTE has been integrated ! Awaits Sprint Acceptance..!!
  6. KC03RW417 (37.07583, -94.38194,Joplin Area, I-44 ) LTE has been integrated. Sent for Sprint Approval.....
  7. TU03XC339 (35.970561, -95.888049) passed the ATP. Sent to Sprint for Approval !!
  8. News ! OK03XC368 (35.40528, -97.54306)LTE has been integrated Today. Sent to Sprint for Acceptance and Approval.!! there are about 10-12 Sites around OKcity-Tulsa area Scheduled to be integrated in next couple of Weeks !
  9. KC08RW461 (37.08639, -94.47972) has passed ATP. Awaits Sprint's Acceptance and Approval....KC03RW413 also has been integrated !!
  10. TU03XC339 (35.970561, -95.888049) is the first site to be getting LTE integrated Tomorrow.. !!!!
  11. News ! Some of sites spread between Tulsa, Oklahoma city, will be integrated (getting 4G) in next two weeks. Sites are OK03SW132 OK03SW187 OK03SW042 OK03SW054 OK03SW041 OK03XC102 OK03SW011 OK03SW039 TU54XC301 TU03XC315.
  12. Update ! KC03RW401 (37.05667, -94.43667)Joplin, MO has been integrated today. Sent to sprint for Acceptance and Approval...
  13. KC03RW412 (36.88083, -94.39111, Neosho, MO) has been integrated and Passed ATP. Sent to Sprint for Acceptance & Approval !!
  14. Update ! KC03RW419 (37.17778, -94.36444) near brroklyn heights, Joplin,MO has passed ATP. Waiting for Sprint Approval...
  15. Sorry, My bad ...Actually Site is not ready yet........
  16. Update ! KC03RW209..near 52 South -- Versailles MO .(38.40889, -92.76167 ) is ready for sprint to Approve and Accept..
  17. # KC03RW411 (36.98472, -94.46222) has been passed ATP. Forwarded to Sprint for Approval.
  18. Site KC03RW412 (Neosho, MO 64850) Scheduled to be integrated next tuesday......
  19. Update Site KC03RW422 (highway 171 S Joplin Area) has been passed ATP. Waiting for Sprint Inspection and approval..
  20. I think Joplin getting more and more site day by day. Ericsson pushing hard in MO market. must be pressure from SPrint. Another siite getting passed by Ericsson by tonight. will update later as site passed the tests....
  21. Just a Heads Up ! Site KC03RW405 (carl Junction, Joplin Area, MO) has passed ATP tests. Waiting for Sprint to Inspect and Approve it.
  22. after KC03RW410, KC03RW403.. another site in Joplin, MO area gonna tested tonight...will update which one is that...
  23. Hahaha !! As per my info Work is not getting start until Summer 2013 in STL.
  24. that i was talking about. this site is up and running LTE. Just need sprint approval (might get it on Monday) to go live in their database. My friend is working as field tester there as sub contractor to Ericsson. he spoke to me yesterday thats why i am getting all info. I do have all sites info with lat-long of MO market.
×
×